Infrastructure

District Projects

Canal lining, buried pipelines, pumping plant rehabilitation and measurement improvements that conserve water and protect delivery capacity.

Active Projects

Main Canal Concrete Lining — Phase IV
Active

Main Canal Concrete Lining — Phase IV

January 2026 – December 2026 (estimated) · Main Canal, Mile 4.2 to Mile 7.8, north of Edinburg

Concrete lining of 3.6 miles of earthen main canal to eliminate seepage losses and stabilize delivery capacity to downstream laterals.

Project details →
Lateral 9 Buried Pipeline Conversion
Active

Lateral 9 Buried Pipeline Conversion

March 2026 – February 2027 (estimated) · Lateral 9, from the Main Canal south to FM 1925

Replacement of 2.1 miles of open earthen lateral with 48-inch buried pipeline, recovering right-of-way and eliminating evaporation losses.

Project details →

Completed Projects

Pumping Plant No. 2 Rehabilitation
Completed

Pumping Plant No. 2 Rehabilitation

May 2024 – August 2025 · Rio Grande River intake, southwest of Hidalgo

Replacement of two river lift pumps, motors and switchgear, with new variable frequency drives and remote telemetry at the District's primary river intake.

Project details →