Completed Project
District-Wide Flow Measurement & Telemetry
Installation of calibrated measurement structures and telemetry at 38 locations throughout the canal system.

Project Overview
Accurate measurement is the foundation of equitable allocation. This program installed calibrated flumes, weirs and acoustic meters at the head of each primary lateral, with data logged and transmitted to the District office each hour.
Staff use the resulting record to balance canal operations, verify deliveries against water orders, and report diversions to the Rio Grande Watermaster.
Timeline
February 2023
Site survey and structure selection
October 2023
First 20 sites installed and calibrated
November 2024
Program complete; all 38 sites reporting